On 2020, February 21 the wooden railing of the deck that goes around the Gönpa was completed.

 

 

The railing now also flanks the left side of the main entrance, given the greater difference in height created by the new deck, now at the level of the internal floor.


 

To complete the area with the external beams of the Gönpa, it will be necessary to wait for the temperature to rise and become stable, without the risk of sudden drops in temperature at night. The first intervention will involve the grouting and complete sealing of the external truss by the Rubner/Holzer company. Merigar will be in charge of the part concerning treating the base and painting it red.

The indispensable sanding of the internal floor that was already damaged and further damaged by rain and humidity during the last structural works has already been taken care of (also financially). The internal floor, in particular the renovation of the external paintings and decorations, and the restoration of the internal decorations will be the subject of a new project in collaboration with the architect Donatella Cavezzali (director of the Higher School of Restoration in Rome and our consultant from the beginning of the project) and our experts in Tibetan iconography, culture, and traditions.

December 7th

The works being carried out by the appointed construction company are coming to an end, but unfortunately the bad weather lately has delayed the final wooden decking work and window fitting.

The lantern has been waterproofed in the points where it was leaking and this will be tested and verified with the next rains.

The wooden decking around the external walkway has been completed along with leveling the doorsteps in line with the external planks and the waterproof sealing of the pillars and beams of the facade.

The Rubner technicians and head of works have verified the suitability of the product Sayerlack to be used to fill cracks in wood so it will be used across the structure wherever it is needed.

As far as finishing the work on the handrail of the walkway and the internal paving, the joiner is on schedule but the external works are very dependent on the weather. We hope the handrail will be completed on the higher areas of the walkway before the building is used for the celebrations in the new year.

The perimeter to the left of the building that was previously without a handrail, is being left the same. Its maximum height difference being 70cm and the minimum 40cm.

The guardrail will be completed taking into consideration aesthetics after everything else has been reassembled.

Externally it remains to modify the floor levels at the entrance in such a way to make it accessible to people with a disability, and when it is an opportune moment to complete the painting of the external wooden structure.

During the last inspection there were noted three windows that needed to be changed, of which two were damaged and one was of defective manufacture.

On 7th October the urgent maintenance work on the Gönpa started again.

The rotted wooden beams on three sides, south, southeast and southwest have been extracted after part of the internal wooden flooring had been removed to allow access. The foundation structure of concrete beams and the supporting sides beam structures from the floor to the roof have been completed.

Because the new masonry structure interferes with the existing electrical channeling, the channeling will need to be displaced and anchored and eventually inspected in order to verify accessibility, for any future maintenance needs.

Before rebuilding the external guardrail it is necessary to guarantee the effectiveness of the drainage systems collecting the rainwater from the roof.

The previous downpipes (that were perforated) have been changed and the drain-wells have been substituted with the covers now at the level of the external walkway, to allow regular inspection and maintenance. The accumulation of leaves and other waste in the wells can lead to the drains being blocked and obstruct the flow of rain water in the case of downpours, leading to nearby internal areas suffering water damage.

Handrail on the external walkway

The joiner responsible for the works on the external handrail is appraising the possibility of re-using some of the original handrail  on the three sides where work is already finished in order to enable the removal of the security scaffolding.

Internal paving

The joiner is also taking care of re-laying the parts of the wooden floor that were removed to facilitate the structural works under the Gompa. This will presumably happen after 7 November.

The re-laying of the pavement will allow the work to place the wooden border sills (which will be painted red) upon which the new windows will be mounted.

Fixing and reintegration of the defective sections of the external facing pillars

The work to treat and protect the wooden pillars and beams needs to be done before winter, so the Rubner workforce will proceed with the maintenance and will repair the larger cracks with glued strips of wood and smaller holes with epoxy filler (balsite) as per the instructions of our consultant expert in wood restoration.

The eventual final painting and protective sealing will be left to Merigar to complete

Last work update before the summer break.

After the cupola lantern had been replaced, in the last week of June, the roofing has been completed.The front sealing trims of the guttering are in place with the copper covering under.

 

Four window structures have been dismantled to enable cleaning of the surrounding wooden structures to allow a full inspection as to their status. Any work needed to fill holes or general repairs will follow.

 

At the same time that the replacement external walkways are being laid, the work to strengthen the structural foundation beams that carry the columns are being assessed and carried out. This will involve using steel girders(4+5) that will be anchored to carry the internal paving beam structures. This will also enable the connecting load bearing support of the external walkway. The defective part of the columns has been removed to the depth of approx 50cm and a new replacement inserted.(you can see that that has a lighter colour with regards to the original). 

The level of the external walkways is now the same as the internal paving and during the repair work all the disparities of height have been eliminatedo. 

 

The structure has been closed to the elements by the mounting of the doors and windows.

 

 

There still remains, after the summer break to do the same work on the other half of the building and to replace the other two beams on the ground level.

All the temporary security structures put in place to protect visitors to the building, need to be monitored and maintained if they suffer any damage or degradation, in addition to people treating them with care and common sense.

Thanks to everyone for their patience and collaboration.

Friday, June 21: The copper roofing is almost complete and the new lantern cupola has been mounted. 

The roofers still have to complete the roof covering on the upper part and mount the top spike with a reconstructed copper sphere at the base, then finalize the restoration with a lightning conductor mesh strip. The work of mounting the new copper guttering will proceed next.

 

Monday, June 24: The materials for the external walkway will arrive and the decking of most of the external walkway will be installed, including the section outside of the main entrance. As previously stated some of the beams and pillars will need to be replaced where necessary.

The work plan is as follows:

  • Cut and remove parts of pillars and support structures that are decayed.
  • Put in position two steel girders, one on each side of the beam supporting the pillar. To the right of the entrance, this work will be carried out under the Gönpa as the beams are below ground level.
  • The beams will be mounted, and the support structure for the walkway and the new part of the pillars replacing the decayed section will be fixed to the existing healthy pillar.

On the southern side of the Gönpa, which is entirely above ground, the framework of the structure rests on beams that are no longer able to carry loads due to their deterioration as a result of poor conservation of the wood.

This necessitates the removal of a strip of the internal flooring in order to access and evaluate the alternative temporary structures needed to facilitate the removal of the beams. These, in turn, will be replaced with either a load-bearing concrete wall or a reinforced concrete girder. All the corresponding support beams and pillars will be examined, repaired, and then reconstructed.

This long and complex work will be scheduled for completion in the latter part of the summer, which means that the refitting of the windows and doors will have to be carried out in the same period.

 

Friday, June 7, 2019. The work in progress is currently focused on the roofing and the external walkway.

Roofing:

The wooden structure has been completed, and 60% of the copper sheeting has been laid.

 

The removal of the existing walkway surrounding the Gönpa has made it possible to verify the state of conservation of the load-bearing beams at the pillars and of the building’s subflooring.

Unfortunately, the situation in the vicinity of the pillars, noted also by the MOST company, is particularly compromised where the beams are concerned (three in particular). Currently, their load-bearing capacity is significantly reduced.

The process of consolidating the pillars and their supporting base is particularly complex but unfortunately absolutely essential.

Regarding the beams, it is been decided to introduce cement blocks at ground level that will serve as intermediate supporting bases and allow this section affected by rot to remain functional. In some instances, the beams of the internal flooring, which rest on these external beams, no longer have a stable base because water has destroyed the fiber of the wood on the upper part of the beams. Accordingly, it is being decided on a case-by-case basis how to intervene.

 

 

 

 May 13-18

In this week, the metal roofing experts of the Rubner company completed the work of laying copper sheeting on the roof of the Cinerarium.

At the Gönpa, the process of reconfiguring the guttering system was begun, starting by dismantling the existing covering, consisting of both copper and sheet metal.

The bays in the south and west have been removed in their entirety and their principal structures have been rebuilt. Together with the metal roofing experts, various test simulations of the gutters were carried out. The existing channel between the edge of the roof and the gutter has represented a critical element for the building in that in some instances it allowed water to infiltrate the wooden structure supporting the Gönpa.

The objective of modifying the configuration of the gutter system is to ensure the correct functioning of the system for collecting and draining water. This will prevent further damage in the future such as the deterioration discovered at the base of some of the pillars.

The positioning of the channel for draining rainwater outward will also simplify future maintenance, for example with ladders to remove accumulated leaves.

Visually and aesthetically it was decided to maintain the existing form of the external side characterizing the appearance of the roof, so the metal roofing team will prepare a sample by next week for final approval of the element to be used.

The engineers are conferring on the form and functionality of the external side of the copper gutter.

The persistent and extensive infiltration of water has led to severe rotting at the base of the pillar, destroying the fiber of the wooden base on which it was anchored and causing a serious deterioration of the sections coming into contact with it.

Once the roofing has been completed and the windows dismantled, the workers will proceed with the substitution of all the deteriorated sections no longer capable of serving a supporting function.



 

External decking
Part of the wooden railing has been removed to make it possible to remove the existing flooring and examine the understructure. The external decking will be redesigned to eliminate the hazardous differences in height at the entrance thresholds and ensure the necessary safety in case of emergency.

 

May 10

While the metal roofing experts continue to lay the copper on the roof of the Cinerarium, Rubner's workers have started to dismantle the external decking and the external walls of the Gönpa.

 

10 May

10 May

10 May

 

May 7: At the Cinerarium, the prep work of installing a substructure required as a base for the copper sheeting was completed and the copper sheeting now covers almost the entire roof.

7 May

7 May

The engineers Vitale and Gaspare inspecting the start of work at the Gönpa.

May 6: At 7 in the morning, an extraordinary phenomenon appeared in the valley near the Gönpa.

6 May

 

6 May

2019, May 6: At 7 in the morning, an extraordinary phenomenon appeared in the valley near the Gönpa.

On May 2, the Rubner company delivered the material and equipment required to start the job.
On May 3, work began on the roof of the Cinerarium. When it was inaugurated in 2015, the work on the Cinerarium’s roof covering had not in fact been completed. The plan is to clad the roof in copper, similar to the Gönpa. Taking advantage of the fact that the workers, equipment, and construction site infrastructure are already in place, we have been able to secure significant cost savings since the companies involved are the same as those carrying out the extraordinary maintenance of the Gönpa.

3 May

 

2 May

On April 12, 2019, the lantern cupola (the small structure mounted on the top of the domed roof) was removed by the technicians of the Teken company to begin the reconstruction.

 

12 April

GO BACK TO THE PROJECT